Romania returns Cernavodă reactors to the grid after drought shutdown and sets up €200m 'Bala 2' scheme to secure Danube cooling water
Unit 2 of Romania's Cernavodă nuclear plant was expected to reach full capacity on 12 November, supplying over 650 MW, with Unit 1 due back on 13 November after a malfunction, ending a roughly three-and-a-half-month drought-related shutdown that cost the country about a fifth of its domestic output. The same day the government created a working group for the Bala 2 project, with an initial €200m, to secure reactor cooling water and Danube navigation.
Background
Cernavodă, Romania's only nuclear plant, normally supplies about 20% of national consumption. Its two reactors draw cooling water from the Danube, and this summer's drought pushed river flow too low for safe operation. Both units were shut down in a controlled way for roughly three and a half months, costing Romania nearly a fifth of its domestic electricity output and forcing large, expensive imports, especially in the evenings, Radio Romania International reported.
What happened
Unit 2 was expected to reach full capacity on 12 November, providing over 650 MW to the grid. Unit 1, which malfunctioned after its restart and needed repairs, was due to reconnect on Friday 13 November, one day later than planned, according to RRI. Authorities expect both units at full power by the weekend.
The same day Transport and Infrastructure Minister Ștefan-Ovidiu Popa announced a government working group for Bala 2, set up after talks with Energy Minister Dumitru Chisăliță. The project aims both to secure water flows for cooling the Cernavodă reactors and to improve year-round navigation on the Danube. The government will initially allocate €200m to launch it, with the estimated total investment at RON 1.2–1.3bn and the remaining funding still to be identified, AGERPRES reported. Popa said a nuclear plant's operation should not depend on the weather, and that he wanted a lasting fix so that this summer's disruption does not recur.
The restart comes as Romania prepares for winter. Gas storage is 43% full, lower than a year ago, though coal stocks are considered adequate. The Energy Ministry is preparing a support scheme for non-household consumers that could start as early as 1 December 2026 and one for vulnerable households from 1 January 2027. Silvia Vlăsceanu of the Association of Electricity Producers warned that higher import costs would likely push suppliers to raise prices by 7–20%.
Analysis
The summer outage is a case study in how climate stress can hit supposedly firm, low-carbon capacity. Nuclear power is central to Romania's decarbonisation plans, including new units at Cernavodă, and to its role as a regional supplier. If river levels become a recurrent constraint, that strategy depends on hydraulic works such as Bala 2 as much as on reactors themselves.
The funding gap is the obvious weakness: €200m is a down payment on a project whose full cost is not yet financed. The regional dimension also matters. Moldova has just completed a high-voltage link that brings Romanian and European electricity into Chișinău, so Cernavodă's reliability now bears directly on its neighbour's effort to reduce dependence on Transnistrian generation.
Sources
- Radio Romania International — Newsflash, November 12, 2026
- Radio Romania International — Measures in the energy sector
- AGERPRES — Transport minister: Bala 2 working group established to boost energy security, improve Danube navigation
- Moldpres — Electricity from European and Romanian markets reaching Chișinău via the Vulcănești–Chișinău power line for more than 48 hours