Policy briefs · Feb 12, 2026

    A year off the BRELL grid: what Baltic synchronisation cost

    One year after leaving the Russian-run BRELL ring, the Baltic grids run stably with continental Europe. Wholesale prices fell slightly in 2025, but keeping frequency stable is a new and visible cost.

    Electric pylons stretch across a picturesque autumn landscape, under a dramatic sky.
    Jiří Dočkal / Pexels
    Contents

    Key takeaways

    • The Baltic grids left the Russian-controlled system on 8 February 2025 and synchronised with continental Europe on 9 February; ENTSO-E confirmed permanent synchronous operation from 25 November 2025.
    • Estonia's average day-ahead price in 2025 was €80.39/MWh, against €87.27 in 2024; Latvia averaged €85.31 and Lithuania €85.73, while Finland averaged €40.48.
    • Elering's frequency-reserve costs reached €56 million from February to July 2025; from January 2026 Estonian consumers and producers pay a balancing capacity fee of €3.73/MWh.
    • The Estonian Competition Authority puts the total synchronisation investment at about €1.6 billion for the three Baltic states and Poland, with EU funding of up to 75 per cent.

    A year ago this week Estonia, Latvia and Lithuania left the power system they had shared with Russia and Belarus since Soviet times and joined the continental European grid. The switch itself went without incident. The more useful question now is what the first year has cost and who is paying. The answer is less about wholesale electricity prices, which fell slightly in 2025, than about the price of keeping the grid's frequency stable, a service the Baltic states used to receive from the Russian system and now have to buy themselves.

    What changed on 8–9 February 2025

    The three grids disconnected from the BRELL ring on 8 February 2025, ran on their own for about a day, and synchronised with the Continental Europe Synchronous Area through Poland on 9 February. For the next nine months they operated in a trial mode while the European system operators checked frequency control and other parameters. On 28 November 2025 ENTSO-E announced that the Baltic operators, Elering, AST and Litgrid, met all key technical requirements and had moved to permanent synchronous operation on 25 November, joining the regional group of continental operators.

    The investment behind this was large. The Estonian Competition Authority puts the total cost for the three Baltic states and Poland at about €1.6 billion, of which Estonia's share was €298 million, with EU funding from the Connecting Europe Facility covering up to 75 per cent. The money went into new and rebuilt lines, synchronous condensers that give the grid the inertia it previously drew from Russian generators, and control systems.

    Prices did not rise over the year

    Fears that synchronisation would push up wholesale prices have not been borne out on an annual basis. ERR reported that Estonia's average day-ahead price in 2025 was €80.39 per MWh, against €87.27 in 2024. Latvia averaged €85.31 and Lithuania €85.73. The difference between the Baltic states is small; the difference with Finland, at €40.48, is large, and it reflects Finland's own generation mix rather than anything to do with synchronisation.

    The monthly pattern tells a more mixed story. February 2025 was Estonia's most expensive month, at €151.85 per MWh. At the time Elering attributed the week's price rise after the switch to less wind, colder weather and higher gas prices, not to the change of grid. The Estlink 2 cable to Finland was also out of service until midsummer, which limited cheaper imports. Even so, Estonia imported 46 per cent of its consumption from Finland in 2025, according to Electricity Maps data cited by ERR. Separating the effect of synchronisation from weather, gas prices and cable outages is not possible with annual averages, and anyone claiming a precise figure should be treated with caution.

    The real cost is balancing

    Inside BRELL, frequency was held largely by the Russian system. Since February 2025 the Baltic operators have had to procure their own reserves, and early on there was not enough capacity in the market. Elering said its reserve costs reached €56 million from February to July 2025 alone, and it raised its annual forecast to about €100 million. It covered the 2025 bill from congestion revenue. From January 2026 Estonian consumers and producers each pay a balancing capacity fee of €3.73 per MWh, which Elering estimates adds about €1.20 a month, VAT included, to the bill of a household using 250 kWh. The fee covers up to €60 million a year; Elering absorbs anything above that. Its chief executive, Kalle Kilk, described the fee, figuratively, as the price of energy independence.

    That figure is higher than earlier estimates suggested, although the measures are not the same. In 2024 LRT reported Litgrid calculations from 2023 that synchronisation would cost an average household about €0.60 a month in Estonia, €0.50 in Lithuania and about €1 in Latvia. Those estimates covered synchronisation as a whole, not only reserves, and the Lithuanian figure assumed consumption of 140 kWh a month, so they cannot be compared directly with Elering's fee, but they point the same way: the running costs came in above the planning figures, at least in the first year.

    Why the bill should shrink

    The costs were concentrated early. Rolands Irklis, who chairs Latvia's AST, told LSM this week that balancing costs were a challenge until July 2025, with March and April the hardest months, and that he expects this year's payments to be two to three times lower than last year's. The main reason is new supply. The operators' own reserves, including battery systems in Lithuania and Latvia and the Kiisa plant in Estonia, reduced total balancing capacity costs eightfold between February and September 2025, according to the three operators. They plan to phase these resources out by November 2028 as commercial batteries and other providers enter the market. Total Baltic demand for balancing capacity is expected to be about 1,600 MW in 2026, so the pace at which private capacity arrives will decide how quickly consumer fees fall.

    Kaliningrad on its own

    The Baltic exit also left the Russian exclave of Kaliningrad without a grid link to mainland Russia. Russia's Energy Ministry said at the time that the region's power plants had a total capacity of 1.88 GW, more than twice its peak consumption, that four new plants had been built between 2016 and 2020, and that five years of annual tests had confirmed the system could run independently. Public information on how the exclave's grid has performed over the year is limited, and there have been no reports of large-scale outages in the sources reviewed here. The Kremlin spokesman, Dmitry Peskov, said at the time that Russia had taken all measures to ensure the uninterrupted and reliable operation of its unified energy system.

    What to watch in year two

    Reliability has held. AST's Irklis said supply reliability in Latvia had improved significantly, and the operators have received more than €100 million in EU funds, shared with Poland, for additional security solutions. The risks he named are hybrid threats, cyberattacks and sabotage. For consumers the key figure is the balancing bill. If Irklis's forecast is right and costs fall by half or more in 2026, synchronisation will look like a one-off investment with a transitional running cost. If new battery and flexible capacity is slow to arrive, the fee will remain a lasting charge on Baltic electricity bills.

    Sources

    Related publications

    Policy briefs · Europe

    Lithuania's Klaipėda LNG Terminal Signs 5-Year US Supply Contract as Baltic Energy Independence Deepens

    Lithuania's floating storage and regasification unit Independence at Klaipėda has signed a five-year liquefied natural gas supply agreement with US exporter Venture Global LNG at rates reported to be approximately 15 percent below European spot LNG prices, reflecting Venture Global's commercial strategy of locking in long-term offtake agreements for its Louisiana export facilities. The contract provides the Baltic region with price-stable gas supply through 2031 and reinforces the region's strategic shift away from Russian pipeline gas.

    Policy briefs · Europe

    Portugal Achieves First Monthly 100% Renewable Electricity Record in European Grid History

    Portugal's national electricity grid operator REN reported that the country's electricity system ran entirely on renewable generation for the full month of September 2026, producing 4,890 GWh against consumption of 4,420 GWh and exporting the 470 GWh surplus to Spain and Morocco. Hydropower contributed 46 percent of generation, wind 38 percent, and solar 12 percent. The achievement marks the first time a European country with a fully interconnected grid has operated on 100 percent renewables for an entire calendar month.

    Policy briefs · Europe

    Moldova Eliminates Russian Gas Dependency After Last Direct Supply Through Ukraine Transit Ends

    Moldova has fully eliminated its dependence on Russian natural gas following the termination of the last remaining direct supply pathway through Ukraine, with the country's entire gas demand now met through the Romanian interconnector and the Iași-Chișinău pipeline. The transition, which ended Moldova's decades-long exposure to supply interruptions and political leverage through energy pricing, was completed through a combination of EU-funded infrastructure investment, Romanian gas supply agreements, and demand reduction measures.