Commentary · Oct 2, 2026

    Kazakhstan's AI pitch rests on cheap coal power and a US export licence

    At this week's AI forum in Astana, officials offered hyperscalers power at about 2.5 cents a kilowatt-hour, a 'data embassy' regime and up to 5 GW of new capacity. The offer depends on a power system that is only now returning to surplus, and on chips that require Washington's approval.

    Distant view of a power plant with cooling towers amidst a vast landscape, illustrating energy production.
    Tanhauser Vázquez R. / Pexels
    Contents

    Key takeaways

    • The Ekibastuz Data Center Valley is planned at about 300 MW, expandable to 1 GW; the Times of Central Asia reports a first 50 MW facility due in June 2027.
    • Kazakhtelecom's chairman said data centres can buy power at around 2.5 cents per kWh and that more than 5 GW of planned new capacity could serve computing.
    • Coal accounts for about 62 per cent of Kazakhstan's electricity; average equipment wear in the sector is put at around 56 per cent, and the government targets a capacity surplus only from 2027.
    • Firebird says its 125 MW allocation at the site has US Bureau of Industry and Security export authorisation; Kazakhtelecom has discussed financing with US and Chinese institutions.

    Kazakhstan used this week's AI & Digital Bridge forum in Astana to make its most explicit offer yet to the world's largest computing companies. President Kassym-Jomart Tokayev promised light-touch regulation, saying the country "must not regulate this sphere to such an extent that promising teams, developments and capital begin to leave for other jurisdictions". He met Nvidia, General Atlantic and the UAE's G42 on the forum's first day. Deputy Prime Minister Zhaslan Madiyev announced work on a "data embassy" regime. The head of Kazakhtelecom spoke of power at around 2.5 US cents per kilowatt-hour and more than 5 GW of new capacity. The ambition is plausible in parts. It is also built on two foundations that Kazakhstan does not fully control: an ageing coal-fired power system and US export approval for advanced chips.

    What was offered

    The centrepiece is Data Center Valley in Ekibastuz, in the Pavlodar region. According to the Astana Times, the project starts at nearly 300 MW and can be expanded to 1 GW. In June the government signed agreements worth up to $10bn with the US firm Firebird and with Nvidia. The Times of Central Asia reports plans for a cluster of about 100,000 advanced GPUs and a first facility of 50 MW due to open in June 2027. Madiyev said construction had begun and that the facility should open in the third quarter of next year. On 1 October Nvidia's vice president Rev Lebaredian outlined plans to join the project's next phase, General Atlantic expressed interest, and Tokayev discussed G42's possible participation with a UAE delegation.

    Madiyev's "data embassy" proposal would let hyperscalers operate in Kazakhstan under a separate international legal framework, with fast access to land and energy at competitive prices. Bagdat Mussin, chairman of Kazakhtelecom, said the country could begin exporting computing power from 2027. He added that Kazakhtelecom had already cut network latency from 90 to 70 milliseconds and that a new fibre link across the Caspian could bring it down to 45–50. Tokayev noted that IT services exports exceeded $1bn last year. Two Kazakh supercomputers using Nvidia H200 chips appeared in the June 2026 TOP500 list, at 104th and 122nd. A separate $2bn sovereign AI hub, to be run by Freedom Holding on Nvidia technology, has a site with 100 MW of available power. Madiyev described the strategy as building all five layers of an AI economy, from energy and chips to cloud access, language models and applications.

    The power question

    The core of the offer is cheap electricity, and here the numbers deserve a closer look. Mussin said that the country should start with the resources it already has, "including coal". Coal provides about 62 per cent of Kazakhstan's electricity, and the average level of wear on power-sector equipment is put at around 56 per cent, according to figures published in August. The government's stated aim is to cover domestic demand fully and reach a capacity surplus from 2027. It plans more than 26 GW of new capacity by 2035, of which 13.3 GW by 2029.

    Scale matters. Kazakhstan expects to generate about 126.5bn kWh this year. A 1 GW campus running continuously would use about 8.8bn kWh a year, roughly 7 per cent of that total. The first 300 MW is manageable. The full 1 GW would be equivalent to a large share of the new capacity the country is adding: about 2.6 GW is due to be commissioned in 2026. In September the Energy Ministry moved to raise ceiling tariffs for 60 generators to pay for repairs and equipment renewal. A price of 2.5 cents for data centres is therefore a policy choice. Someone, whether households, industry or the budget, will bear the cost of building the plants that make it possible.

    There is also a climate cost. Computing powered by Kazakh coal plants would carry a heavier emissions footprint than computing powered by most alternative sources. Mussin's remarks suggest Astana is betting that price and speed matter more to buyers than the source of the power. Some buyers may agree. Others will not.

    Chips, finance and two capitals

    Madiyev was frank that "sovereign" AI does not mean self-sufficiency. Kazakhstan does not produce chips, he said, so it needs partners in both the West and the East and good relations with the agencies that run export controls. That is the second dependency. Firebird says its 125 MW allocation at Data Center Valley has export authorisation from the US Commerce Department's Bureau of Industry and Security. Further tranches of Nvidia hardware are likely to need the same approval.

    Financing points in another direction. In September Kazakhtelecom's chairman said the company was in talks with financial institutions in the US and China to borrow several billion dollars for the valley, alongside bonds on the Astana International Financial Centre and loans from the Development Bank of Kazakhstan. Pravda.ru, reporting his comments, added that the final cost could reach several tens of billions of dollars. Combining Chinese money with US-licensed chips is not prohibited, but it is the sort of arrangement that export-control officials examine closely. Kazakhstan's "data embassy" idea, giving foreign operators a separate legal framework, may be partly intended to reassure them.

    What would make the plan credible

    • A published power supply arrangement for the campus showing which plants serve it, at what tariff, and who funds the new capacity.
    • Clarity on whether the 50 MW first phase opens in June or in the third quarter of 2027, since officials are giving different dates.
    • The legal text of the data embassy regime, and how it handles Kazakh law enforcement access and US end-use conditions.
    • The source of the debt: the mix of US, Chinese and domestic lenders will matter for future export licences.

    Kazakhstan's strengths are real: land, energy resources, a fast-moving state and experience running Nvidia systems. Whether it becomes a regional computing hub will depend less on announcements at forums than on two quieter questions: whether its power system can supply a gigawatt without strain at home, and whether Washington keeps licensing the chips while Beijing helps pay for the buildings.

    Sources

    Related publications

    Commentary · Caucasus

    The region’s AI laws stop where the drones start

    Kazakhstan and its neighbours are regulating civilian AI while buying drones. The rules for autonomous weapons are being written in Geneva, where Armenia and Azerbaijan are not parties.

    Policy briefs · China & Asia-Pacific

    India Confirms Gaganyaan Crewed Mission Launch Window for January 2027

    The Indian Space Research Organisation confirmed on October 18 that the Gaganyaan crewed spacecraft mission is on track for a January-March 2027 launch window, making India the fourth country to independently launch humans to orbit. The mission profile calls for a three-person crew to orbit for 72 hours aboard the LVM3 launch vehicle from Sriharikota. The announcement follows the successful unmanned Gaganyaan G1 orbital test in July 2026 and the verified recovery of the crew module in the Bay of Bengal.

    Reports · China & Asia-Pacific

    India and Japan Sign Semiconductor Supply Chain Partnership, Co-Investing USD 8 Billion in Advanced Packaging Facilities

    Indian Prime Minister Narendra Modi and Japanese Prime Minister Sanae Takaichi signed a Semiconductor Supply Chain Partnership in New Delhi on 3 October 2026, committing a combined USD 8 billion to build advanced chip packaging and testing facilities in Gujarat and Tamil Nadu. The partnership, backed by Japan's Rapidus consortium and India's Tata Electronics, targets production of 3D chip packages for automotive and industrial applications by 2029.